Al-Sahafa ( Press ) Tunnel Package General chart
Construction of the infrastructure for BRT Al-Sahafa Tunne
Project Description :
The project includes the construction of two separate bridges dedicated to BRTwith 500 meters long for each bridge, the rehabilitation of Al- Sahafa tunnel the redesign of Al- Sahafa intersection to convert it from a signalized intersection to a roundabout, as well as the works of sidewalks and rainwater drainage network .
Contractor
Haddadin Engineering and Contracting Company
Supervision
Greater Amman Municipality Department of BRT infrastructure
Tender value (not including provisional sum
Provisional sum
Tender value (including provisional sum)
(5489183) JOD
Commencement date
19/08/2017
Project duration
(365) days