Loading

Tarek-Ain Ghazal Package General chart

The construction of BRT infrastructure for Tareq Junctio

Project Description:

The project includes the construction of a BRT route in Al-Shaheed Street for (1.3) km, and the reconstruction and expansion of the original road from both sides, the construction of Amman- Zarqa Tunnel and Al- Hashemi Tunnel /Tabarbour, as well as the construction of a bridge and a roundabout and the complementary works of roads, sidewalks, lighting and the rainwater drainage network, in addition to the works of the main terminal for passengers and all related architectural, electrical and mechanical works.

Contractor

Haddadin Engineering and Contracting Company

Supervision

Greater Amman Municipality /Department of BRT Infrastructure

Tender value (not including provisional sum

( 23,868,900.346 ) JOD

Provisional sum

2,663,000 JOD

Tender value (including provisional sum)

(26531900.346) JOD

Commencement date

17/06/2019,(730) Days

Project duration

Design charts