Al-Kindi street Package General chart

Project: Construction of BRT infrastructure on Al-Kindi Street and Al-Sharif Nasser Bin Jamil Stree

- Project description:

The project is divided into two packages

• Package 6 Al-Kindi Street: the construction of a 1,187 km BRT lane that runs from the intersection of Wadi Saqra to Princess Basma Street, as well as sidewalks, retaining walls and rainwater drainage network.

• Package 10 Al-Sharif Nasser Bin Jamil Street: The construction of a 2.1 km BRT lane that extends from the intersection of Wadi Saqra to the intersection of the sports city . It includes the construction of a tunnel with (760 meters) long , walls of the tunnel (230 meters) and a bridge with a length of (180) meters , walls of the bridge with a length of (137) meters in addition to the works of sidewalks , retaining walls and rainwater drainage network.

Contractor

Haddadin Engineering Contracting Company

Supervision

Greater Amman Municipality Department of BRT Infrastructure

Tender value (not including provisional sum

(11,242,372.9) JOD

Provisional sum

(1,746,250) JOD

Tender value (including provisional sum)

(12,988,622.9) JOD

Commencement date

24/7/2019

Project duration

420 days